The flue gas purification project of the Nankang household waste incineration power generation project in Ganzhou City, Jiangxi Province, undertaken by Huaxing Oriental, has passed 72+24 hour trial operation
2023.08.31
The flue gas cleaning (FGC) project undertaken by Huaxing-east for Nankang waste incineration power plant in Ganzhou, Jiangxi passed 72+24 hours trial operation on April 11, 2023.
伟德国际(victor1946)官方网站-Officials Website
The plant total capacity is 2000 t/d and will be constructed in 2 phases. The 1st (current) phase of the plant has a treatment capacity of 1000 t/d of municipal solid waste. Two 500 t/d incineration lines will be constructed, along with the installation of one condensing steam turbine generator with rated power 30 MW (expansion of 1000 t/d production line for 2nd phase reserved). The FGC process applied "In-furnace SNCR + semi-dry rotary spray + dry powder injection + activated carbon adsorption + bag filter + fly ash conveying, storage and stabilization". It is an EPC project of Huaxing.
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
Huaxing's achievements in Jiangxi Province include Jiujiang Duchang, Nanchang Hongcheng, Yichun, Nanchang Quanling, Yichun Fengcheng, Ganzhou Nankang, Longnan, Jingdezhen, etc.
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website
伟德国际(victor1946)官方网站-Officials Website

伟德国际(victor1946)官方网站-Officials Website

For more information, please click or scan below!
Follow us!
伟德国际(victor1946)官方网站-Officials Website

【网站地图】